CURRENT STATUS (dated: 12 Dec 2012)
Project has started on September 4th 2012 and it has been reached the BDR milestone related to Requirements and Specification definition.
Requirements deliverables will cover the following aspects:
- Operational scenario
- SATURN prototype requirements
- End-to-End SATURN system requirements
- Service requirements
Specification deliverables are focused on major SATURN prototype components:
- Antenna electromagnetic section specification
- Antenna amplification and communication section specification
- Onboard gateway specification
- Plotter specification
The design phase is about to start, and it will require 3 months. During the design phase the Implementation phase will start also, including tests, to be completed in 7 months.