SATURN Project - Phase 1

PROJECT PLAN

The project started in September 2012 in the framework of ARTES 5.2 ESA projects (Telecom – Technology, Non-competitive industry-initiated activities). The project is expected to have a duration of 13 months.

The project plan is based on following main WPs:

  • WP2 - Requirements Definition
  • WP3 - Specification Definition
  • WP4 - Design
  • WP5 - Implementation and Verification
  • WP6 - Integration and Test